Equipment at a glance
- Model / engine reference
- GE LM6000 PD SPRINT / ESN 192-282
- Plant output class
- Approximately 46 MW; actual site performance to be established
- Frequency / generator voltage
- 50 Hz / 11.5 kV; 60 Hz compatibility or conversion not confirmed
- Engine history
- 2009 manufacture; GE factory-refurbished engine installed in 2021, per dossier
- Generator
- Brush BDAX 7-290ERJT — 50.8 MW / 63.5 MVA, 0.8 PF, per dossier; distinct from plant output class
- Gearbox
- Lufkin NFVQ2419-D, 1.209:1 ratio
- HRSG
- DKME Korea DKS2107H01 — 52 t/hr, 103 barg, 313°C; single-pressure natural circulation
- Fuel / combustion
- Natural gas plant; triple annular combustor per supplier
- Indicative purchaser-facing price
- USD 27,000,000 EXW, subject to seller confirmation and final contract
- Removal scope
- Complete cogeneration plant requiring dismantling
- Current location / hours / starts
- To be confirmed with current dated evidence
- Warranty / shipment schedule
- Not yet agreed
Complete cogeneration equipment scope
- GE LM6000 PD SPRINT turbine and enclosure, Brush generator and Lufkin gearbox.
- HRSG and two Ariel JGC/4 natural-gas booster compressors. Dossier readings: compressor A approximately 97,280 hours; compressor B approximately 5,800 hours. These are historical component readings, not current engine hours.
- ABB gas circuit breaker, 4,000 A / 11 kV as described. Reconcile its nameplate, duty and integration against the 11.5 kV generator.
- Woodward / MicroNet Plus controls and Bently Nevada 3500 vibration monitoring.
- ABB 800xA v5.1 DCS, ESD and electrical SCADA; virtualized on new hardware in 2023 per dossier.
- Eagle MERV 17 two-layer inlet filtration with pulse-jet cleaning, upgraded in 2024 per dossier.
- CO₂ fire suppression, Siemens Oxymat/Ultramat CEMS, hydraulic starter, gas chromatograph and spare-parts inventory as described. Final component schedule must establish completeness.
Maintenance chronology — keep plant and engine hours separate
| Date | Supplier-recorded event |
|---|---|
| July 2012 | Plant commissioned; dossier reports GE CSA maintenance throughout operating life. |
| September 2017 | Hot-section replacement at 41,393 package hours. |
| March 2021 | GE factory-refurbished engine exchange at 67,853 package hours. |
| 2023–2024 | DCS virtualization, intake filtration upgrade and HCU replacement. |
| December 2024 | GE semi-annual inspection and borescope recorded engine as fully serviceable at that time. |
67,853 hours is a historical package reading at the 2021 engine exchange, not the current engine-hours total. Obtain present hours, starts, operating/shutdown status and original maintenance/borescope records. The December 2024 result is historical and does not establish current condition.
Supplier plant photographs


Commercial terms and removal responsibilities
Indicative price: USD 27,000,000 EXW, including the source intermediary’s remuneration, subject to current seller confirmation, final scope, satisfactory inspection and definitive contract.
Dismantling, packing, loading, transport, insurance, import charges, installation and any frequency conversion must be expressly allocated and separately priced where not included. All plant components require dismantling. Warranty/as-is terms, price validity and a binding shipment schedule have not been agreed.
This is a 50 Hz plant. Do not assume 60 Hz compatibility. No deposit amount or payment milestone is established for this position; any payment schedule must be agreed in the final contract.
Technical review, inspection and purchase
- Send the purchasing legal entity, project country, required frequency, delivery target and nominated technical reviewer. Confirm that a 50 Hz complete cogeneration plant fits the project.
- Establish confidential buyer registration, applicable confidentiality/non-circumvention documents and intermediary fee protection before an authorized introduction. Review the actual documents before signing. Funding verification follows an agreed confidential qualification process.
- Obtain current dated proof of existence, equipment identity, present operating or shutdown status, ownership or authority to sell, and the final equipment schedule before travel or a deposit commitment.
- Agree inspection access, site contact, dates, safety requirements, permitted photographs and tests, independent inspector and travel costs. Reconcile nameplates, component serials, preservation and maintenance records. Running tests or additional borescope work require specific authorization.
- Following satisfactory diligence, agree technical acceptance, title transfer, final scope, warranty/as-is terms, delivery obligations and protected payment instructions in the definitive contract. An inspection is not unconditional purchase acceptance.
Source and verification status
Original two-page supplier dossier available through the confidential qualification process. The opportunity comes through supplier/intermediary channels, not a verified direct-owner mandate. Confirm current proof of existence tied to ESN 192-282, ownership or authority to sell, final scope and inspection access before travel. This is separate from the LM2500 offerings.
