Equipment at a glance
- Quantity / model
- Two GE LM2500+G4 DLE turbine-generator packages
- Supplier-stated ISO output
- 33.6 MW each; 67.2 MW combined simple-cycle rating at 60 Hz
- Frequency
- Presented at 60 Hz; dossier describes 50/60 Hz capability. Delivered configuration requires agreement.
- Core manufacture / fired hours
- 2013 / zero fired hours, as reported by supplier
- Assembly references
- 678-192 and 678-186; additional component serials require reconciliation
- Generators
- Two Brush BDAX 71-193ER; dossier states approximately 45 MVA, 13.8 kV, 60 Hz, 3,600 rpm; nameplate confirmation required
- Preservation
- Periodic high-speed crank testing reported; current records required
- Reported location
- Installed in China, per original dossier; exact site and access subject to verification
- Package-only indicative total
- USD 98,000,000 for both packages; ex-site, as-is/where-is
- Complete-plant indicative total
- USD 102,000,000; includes two HRSGs and approximately 25 MW / 50 Hz steam-turbine package
- Warranty
- No equipment warranty under source as-is sale terms
Two purchase scopes. One clearly defined equipment schedule.
| Scope | Two gas-turbine packages | Alternative complete plant |
|---|---|---|
| Indicative total | USD 98,000,000 | USD 102,000,000 |
| Gas turbines & alternators | Two packages | Two packages |
| GT auxiliaries | Per agreed equipment schedule | Per agreed equipment schedule |
| HRSGs / steam turbine | Excluded | Two HRSGs and approximately 25 MW steam-turbine package |
| Cooling towers / transformers / plant controls | Excluded | Described in complete-plant scope; final inventory required |
| Frequency limitation | Delivered GT frequency to be agreed | Steam turbine is 50 Hz; 60 Hz conversion requires separate engineering and pricing |
The package-only offering is not a turnkey, ready-to-operate power plant. Required controls, frequency work, dismantling, packing, freight, insurance, duties, installation and commissioning must be separately scoped and priced.
Configuration, performance and preservation
- DLE aeroderivative gas turbines. Supplier nominal ISO basis: natural gas, 15°C, sea level, 60% relative humidity and no inlet/exhaust losses. Site output is not guaranteed by the ISO rating.
- The dossier references approximately 39.4% LHV efficiency, approximately 527°C exhaust temperature and nominal 25 ppm NOx/CO. These are supplier/reference values, not site-specific emissions or performance guarantees. Verify fuel configuration, permit requirements and emissions controls.
- Included GT auxiliaries are described as hydraulic systems, inlet filtration, ventilation, turbine/generator lube oil, vibration monitoring, CO₂ fire protection and water wash. Verify physical completeness.
- The dossier describes packaging around 2019, site delivery in 2021 and high-speed crank commissioning in 2022 without firing because natural gas was unavailable. Monthly crank preservation is reported; obtain current logs.
- The dossier also photographs component S/N 678-154. Reconcile gas-generator, power-turbine and generator identities with the stated 678-192 / 678-186 assemblies before acceptance.
- Complete-plant controls are described as Fanuc RX3i sequence control and Woodward MicroNet Plus fuel control. Confirm the entire control scope and integration work.
- The dossier estimates approximately 92–95 MW combined-cycle output. This is a planning estimate, not verified net output or a ready 60 Hz plant rating.
Supplier photographs — historical equipment views




Historical supplier photographs are for identification; they do not confirm current condition, completeness, availability or ownership.
Commercial basis and delivery
Both figures are indicative purchaser-facing totals supplied through the intermediary, including its stated remuneration; no separate intermediary brokerage fee is added to those figures. Final selling price, current availability and scope require seller reconfirmation and contract. The $102M complete-plant alternative replaces the $98M package-only total; it is not an additional charge.
The supplier proposes a refundable 0.25% exclusivity deposit for 30 days of diligence. Beneficiary, amount, refund triggers, deadlines and release terms must be documented and accepted first. No refund guarantee or payment instruction is made here. Proposed subsequent milestones are 50% to begin dismantling/packing and 50% when packed and ready to ship, subject to contract and agreed payment security.
The source estimates approximately 10–14 weeks from first payment to a US customer location. This is an unconfirmed planning programme, not a delivery commitment or a schedule for other countries. Customs classification, duties and any relief require project-specific confirmation.
Technical review, inspection and purchase
- Send the purchasing legal entity, project country, required frequency, delivery target and nominated technical reviewer. Select the two-package or complete-plant scope in an asset-specific LOI.
- Establish confidential buyer registration, applicable confidentiality/non-circumvention documents and intermediary fee protection before an authorized introduction. Review the actual documents before signing. Funding verification follows an agreed confidential qualification process.
- Obtain current dated proof of existence, equipment identity, present operating or shutdown status, ownership or authority to sell, and the final equipment schedule before travel or a deposit commitment.
- Agree inspection access, site contact, dates, safety requirements, permitted photographs and tests, independent inspector and travel costs. Reconcile nameplates, component serials, preservation and maintenance records. Witnessed crank testing requires authorization.
- Following satisfactory diligence, agree technical acceptance, title transfer, final scope, warranty/as-is terms, delivery obligations and protected payment instructions in the definitive contract. An inspection is not unconditional purchase acceptance.
Source and verification status
This is an intermediary-sourced opportunity, not an asserted direct-owner mandate. The owner, contracting seller, authority, protected introduction and inspection access remain to be verified. Original 11-page supplier dossier available through qualification. This position is separate from other LM2500 fleets or proposals; their prices, quantities and scopes do not apply here.
